Development Plan Status and Plan Preparation Progression

Development Plan In-Force

Bridgend Local Development Plan (2006 – 2021)

Adopted 18 September 2013

Local Development Plan Preparation

Bridgend Local Development Plan (2006 – 2021)

Formal preparation commenced 7 December 2005

Delivery Agreement and Sustainability Appraisal Scoping Report

Consultation period 3 August – 8 September 2006

Delivery Agreement submitted to Welsh Assembly Government : 6 October 2006

Delivery Agreement agreed by Welsh Assembly Government : 6 November 2006

Sustainability Appraisal Scoping Report approved by Council: 28 December 2006

Candidate Sites / Site Register

Call for sites 9 November 2006 to 31 January 2007

Candidate Site Register published 15 May 2007

LDP Vision & Strategic Growth Options

Stakeholder Consultation 28 June – 10 August 2007

LDP Pre-deposit Proposals

Consultation 12 February 2009 – 31 March 2009

Initial Consultation Report published 19 October 2009

Draft Candidate Site Assessment Procedure Consultation

23 October 2009 – 20 November 2009

Deposit Plan

Consultation 4 July 2011 - 9 September 2011

Alternative Sites

Consultation 28 October 2011 - 9 December 2011

Consultation Report

Published 11 July 2012

Submission

31 July 2012

Examination

Amended Sites Consultation

August 2012 onwards

21 February 2013 – 9 April 2013

Inspector's Report

Received 26 July 2013

Adoption

18 September 2013

Summary of LDP Preparation Timetable

 

Stage

Date

Stage 1

Review and Develop Evidence Base for LDP

April 2006 – July 2012

Stage 2

Delivery Agreement Consultation Period

April 2006 – January 2007 August 2006 – September 2006

Stage 3

Pre-Deposit LDP Participation & Consultation Consultation Period

October 2006 – October 2009
January 2009 – March 2009

Stage 4

Deposit LDP and Feedback Consultation Period

September 2009 – July 2012 July 2011 – September 2011

Stage 5

Advertisement of ‘Alternative Sites’ Consultation Period

October 2011 – December 2011 October 2011 – December 2011

Stage 6

Submission and Examination

July 2012 – August 2013

Stage 7

Inspectors Report

August 2013 – September 2013

Stage 8

Adoption

October 2013 – December 2013

Stage 9

Annual Monitoring Report and Review of LDP

January 2014 onwards

Source: Bridgend LDP Delivery Agreement – Revised September 2012