BCBC Road Works Report: 14th November 2008 to 20th November 2008

Rating - Low

High

(Intermittent Width Restrictions)

Location:

A48 Barn Hill (adjacent to Broadlands Estate), Bridgend

Start Date:

17/11/08

Finish Date:

20/11/08

Details:

Drainage works

Contractor:

Highway Construction Services for Bridgend County Borough Council

(Temporary Traffic Signals)

Location:

A4063 Maesteg Road, Llangynwyd

Start Date:

17/11/08

Finish Date:

21/11/08

Details:

Frame and cover installation works

Contractor:

Daniel Contractors for DCWW

(3 way Temporary Traffic Signals)

Location:

A4065 Bryn Road junction of Heol-Yr-Ysgol, Brynmenyn

Start Date:

20/11/08

Finish Date:

20/11/08

Details:

Apparatus inspection works

Contractor:

Enterprise Contractors for BT Openreach

(Intermittent Width Restrictions)

Location:

A4063 Aberkenfig By-Pass, Aberkenfig

Start Date:

06/10/08

Finish Date:

20/11/08

Details:

Drainage works

Contractor:

Highway Construction Services for Bridgend County Borough Council

(Temporary Traffic Signals)

Location:

A4063 Llwydarth Road, Maesteg

Start Date:

03/11/08

Finish Date:

14/11/08

Details:

Sewer upgrade scheme

Contractor:

Morrison Construction contractors for DCWW

(Intermittent Temporary Traffic Signals)

Location:

A4063 Cymer Road/Caerau Road, Caerau

Start Date:

22/09/08

Finish Date:

06/02/09

Details:

Works associated with access road construction for new school

Contractor:

Dyer and Butler contractors for Bridgend County Borough Council

(Temporary Traffic Signals)

Location:

B4282 Castle Street, Maesteg

Start Date:

19/11/08

Finish Date:

21/11/08

Details:

Service renewal works

Contractor:

Daniel Contractors for DCWW

(Temporary Traffic Signals)

Location:

B4280 Penprysg By-Pass (Penprysg Roundabout to High Street Heol Y Cyw stretch), Pencoed

Start Date:

14/11/08

Finish Date:

19/11/08

Details:

Supply works

Contractor:

Balfour Beatty contractors for WPD

(Intermittent Width Restrictions)

Location:

B4281 High Street, Kenfig Hill

Start Date:

24/10/08

Finish Date:

20/11/08

Details:

Footway works

Contractor:

David Williams Contractors

(24 Hour Temporary Traffic Signals)

Location:

Heol Simonston, Coity

Start Date:

29/09/08

Finish Date:

19/12/08

Details:

Works associated with new by-pass road

Contractor:

Alun Griffiths Contractors

(Width Restrictions)

Location:

Brackla Street, Bridgend

Start Date:

14/11/08

Finish Date:

20/09/08

Details:

Ducting works

Contractor:

Enterprise contractors for BT Openreach

(Temporary Traffic Signals)

Location:

Brackla Way, Brackla

Start Date:

05/11/08

Finish Date:

14/11/08

Details:

School amalgamation scheme

Contractor:

Jehu Project Services for Bridgend County Borough Council

(24 Hour Temporary Traffic Signals/Intermittent 3-way signals)

Location:

Heol West Plas junction Main Avenue, Litchard

Start Date:

04/09/08

Finish Date:

19/12/08

Details:

Works associated with new development

Contractor:

Alun Griffiths contractors

(Intermittent Stop/Go boards)

Location:

Heol West Plas, Litchard

Start Date:

14/11/08

Finish Date:

20/11/08

Details:

Ducting works

Contractor:

Virgin Media

(Temporary Road Closure 06:30 to 17:00)

Location:

Angel Street, Bridgend

Start Date:

16/11/08

Finish Date:

16/11/08

Details:

River walkway scheme

Contractor:

Carillion contractors for Bridgend County Borough Council

(Temporary Road Closure)

Location:

Esplanade Avenue from junction of Blundell Avenue to junction of Esplanade, Porthcawl

Start Date:

10/11/08

Finish Date:

19/12/08

Details:

Sewer upgrade scheme

Contractor:

Morisson Construction for DCWW

(Intermittent Temporary Traffic Signals)

Location:

Esplanade, Porthcawl

Start Date:

10/11/08

Finish Date:

23/01/09

Details:

Sewer upgrade scheme

Contractor:

Morisson Construction for DCWW

(Temporary Road Closure)

Location:

Pen-Y-Cae Lane, Pen-Y-Cae

Start Date:

13/11/08

Finish Date:

19/12/08

Details:

Essential river bridge repairs

Contractor:

Highway Construction Services for Bridgend County Borough Council

(Intermittent Temporary Traffic Signals)

Location:

Bettws Road, Bettws

Start Date:

27/10/08

Finish Date:

20/11/08

Details:

Footway works/Carriageway patching

Contractor:

Centre Great contractors for Bridgend County Borough Council

(Temporary Traffic Signals)

Location:

Fairfield Avenue, Maesteg

Start Date:

17/10/08

Finish Date:

20/11/08

Details:

Works Service renewal works

Contractor:

Daniel Contractors for DCWW

(Intermittent Width Restrictions)

Location:

Metcalfe Street junction Coegnant Road, Caerau

Start Date:

22/09/08

Finish Date:

20/11/08

Details:

Footway works

Contractor:

Centre Great contractors for Bridgend County Borough Council